As part of our program to support sustainable community development, Cominco has undertaken the rehabilitation works of the secondary school of the Hinda village during the months of April and May 201

Cominco's team working on the rehabilitation of the Secondary School

The work programme included:

  • Repaint three classrooms including the blackboards
  • Replace most of the roof (damaged steel sheets)
  • Plaster the interior walls of each classroom
  • Demolish and replace the concrete floors of the classrooms and the corridor

The total cost of this work is estimated at 18,370 euros and required a labour of 145 man-days. Cominco mainly used its own employees.